Estimated Project Schedule


Warrensburg

Warrensburg


Lexington

Lexington


FAQs

FAQs


Environmental Studay

Environmental

Study


Schedule

Schedule


 

Warrensburg project schedule

  • January 13, 2009: Early notice to proceed
  • Roadway work to start on north side of US 50 to construction most of the ramps and the US 50 temporary bypass
  • April 30, 2009: US 50 temporary bypass open with one-lane traffic in each direction
  • May 1, 2009: Start of excavation for MSE Walls and US 50 bridges
  • Construction of the bridge over Bear Creek and UP railroad in 2009
  • October 31, 2009: US 50 open to two-lane traffic in each direction on new bridges and rebuild eastbound lanes
  • Excavation work will proceed north to south in 2009 and early 2010
  • Rest of bridge construction in 2010
  • Paving in 2010, finished in late summer or early fall

Lexington project schedule

  • February 2009: Groundbreaking ceremony
    Survey work begins
  • March 2009: Excavation and ground work
  • June 2009: Construct Higginsville Road
  • March 2010: Begin construction for the "Gap" roadway
  • May 2010: Ramp construction at the interchange
  • July 2010: Signing, rumble strip installation and striping for new roadway.
  • August 2010: Paving for remaining shoulders and final striping
  • September 2010: Project completion


 

   
   